:: Personal Web Site ::

B Tech (Civil) - IIT Delhi
MCA (IGNOU Delhi)
DWM (CICC, Japan)
 Chartered Engineer - MIE

Technical Rules

Binay Kumar Pandey

Home ] Up ] 101 Manangement Tips ] CICC - Japan ] Free Book Review* ] Down Loads ] Current Projects ] Personal ] My Memoir ] Link Exchange ] Views of Visitors ] भोजपत्र देवनागरी  Hindi - Section ]

Section : Technical Rules

 

 

TECHNICAL RULES FOR STEEL STRUCTURES

01. STEEL STRUCTURES

02. MATERIALS FOR CONSTRUCTION

03. METHOD OF CONSTRUCTION

goto database

01. STEEL STRUCTURES

GOTO TOP

01.01 Description of work

Steel structural works shall include :

- The preparation and supply of G.A. drgs.,shop fabrication & erection drgs., material indents, shop material lists, site bolt list and despatch documents/sheeting etc.

- The supply, fabrication, shop painting, transportation, delivery and storage of all steel structures, sheeting/glazing including site bolts, electrodes, sheeting fixtures etc. complete in all respects.

- Erection (including tools, tackles, cranes and any staging or false work required for erection), handling, transport and rectification of damaged structures, fixing, bolting, welding, alignment, levelling etc. of all steel structures, sheeting/ glazing materials etc. complete in all respects.

- Painting of steel structures after erection.

01.02 List of steel structures

The steel structures shall cover complete steel construction for the different units of the steel plant and shall essentially include but not limited to the following items as required :

- Columns, anchor bolts, column bracing.

- Main roof girders/trusses, purlins, sag rods, roof bracing, ties, eaves beams, ridge beams and all intermediate roof beams/trusses, roof monitors.

- Crane runway girders, horizontal surge girders, vertical and horizontal auxiliary girders, crane rails, rail clips, crane stops, access stairs, platforms including handrails.

- Wall and gable framing including posts, wind girders, girts, sag rods, louvres and bracings.

- Floor beams, chequered plate floorings, open mesh/grid flooring, handrailing for access stairs, platforms for maintenance and repairs, roof lamp service platforms.

- All access stairs complete with treads, landings, handrail, ladders complete with safety hoops.

- Gutters and downpipes.

- Repair hoist beams, platforms and access stairs.

- Windows and glazing.

- Steel gates, doors, shutters, metallic partitions.

- All fasteners (including site requirements) splicing materials, site erection requirements including shims and packplates for levelling (5% adhoc extra for site fasteners and requirements).

- Wear resistant lining plates and heat shields.

- Bins, hoppers, silos, chutes and their supporting structures.

- Conveyor galleries including trusses, floor and roof structures, wall framing, supporting trestles, bearings, structures for take up towers and protection cages for counter weights complete with platforms and stairs.

- Fabricated pipes and their supports, saddles, platforms, stairs,ladders, handrails, accessories, etc.

- Sheeting complete with all flashings and fasteners in accordance with the specifications (5% adhoc extra fasteners for site requirements).

- Surface preparation and painting in accordance with the specifications.

02. MATERIALS FOR CONSTRUCTION

 GOTO TOP

- Materials for construction shall generally be of mild steel in compliance with relevant Indian specification and standards. However, wherever required, high strength structural steel may be used in compliance with relevant standards.

- Bolts, nuts and washers shall conform to the appropriate standards.

- Electrodes for welding shall conform to the relevant standards and shall be chosen according to the welding procedure to be adopted and the quality of metal to be welded. The properties of weld and the heat affected zone material shall not be inferior to the parent metal properties.

- Material for roof and wall sheeting shall be, unless otherwise specified, corrugated galvanized iron sheets with zinc coating of not less than 600 g/mē (nominal) on both sides of sheets taken together. The thickness of the sheets for roof and wall shall not be les than 1.0 mm (20 gauge) and 0.8 mm (22 gauge) respectively.

- Flashing shall be atleast 1.0 mm thick (20 gauge) galvanised iron sheet with zinc coating not less than 600 g/mē (nominal) on both sides of sheets together.

- Translucent sheets shall be fibre glass reinforced polyester sheets of matching profile as per appropriate standards.

03. METHOD OF CONSTRUCTION

 GOTO TOP

- The mode of construction shall be either welded or bolted but limiting the site work to minimum possible.

- Method of splicing shall be similar to the mode of construction adopted for structures.

- Roof and wall sheets shall be fixed to purlins and girts by stainless steel top speed screws/ galvanized J hook bolts, each complete with neoprene and stainless steel/galvanised washers. The connection shall ensure water leak proofness into the buildings/conveyor galleries. The spacing of these screws/bolts shall be sufficient to prevent uplift of sheets by suction. The roof and wall sheets shall be stitched together at their edges by using studs, rivets or screws. The over-laps of sheetings shall be sufficient to prevent ingress of rain water.

04. TECHNICAL SPECIFICATION FOR FABRICATION OF STEEL STRUCTURES

 GOTO TOP

04.1.0 GENERAL

This specification shall apply to steelwork in buildings and general structural work. For technological structures additional stipulations shall be considered.

04.2.0 SCOPE OF WORK

The scope of work under fabrication includes, but not limited to, the following :

a) Preparation and supply of material indents, bolt lists, bought out items list.

b) Procurement and collection of all steel materials from stockyards/stores, including loading, transportation, unloading and stacking and storing on skids or supports.

c) Procurement and collection of all consumables like bolts, nuts, washers, rivets, electrodes, paints, shims, packs, etc. including allowance for spares and wastage and getting approval.

d) Preparation and submission of general arrangement drawings, fabrication drawings, modification/ rectification sketches, as made drawings, erection drawings, bill of materials,drawing office despatch lists/shipping documents.

e) Preparation and submission for approval of design calculation for non-standard connections and temporary bracings.

f) Cold straightening of sections and plates whenever they are bent and kinked.

g) Fabrication of all steel structural components covered under tender drawings, design drawings and generally described under scope of the project.

h) Making arrangements for conducting tests, such as chemical analysis, physical and mechanical tests on raw materials where specified/as directed by the Engineer.

i) Making arrangement for providing all facilities for conducting ultrasonic, x-ray or gamma ray tests on butt welds; getting the tests conducted by reputed testing laboratories; making available test films/graphs, reports and interpretation.

j) Assembly of steel structural components at shop, wherever required.

k) Preparation of steel structural surfaces for painting by power tools or sand blasting as provided in the specifications/drawings.

l) Application of one primer coat of paint, at shop as specified in the design drawing/specifications.

m) Loading, transportation from site of fabrication to site of erection, unloading at site of erection, of all steel structural components/units /assemblies.

04.3.0 DRAWINGS

04.3.1 The contractor shall prepare design drgs. showing general arrangement/marking, fabrication drawings, erection drawings, bill of materials, drawing office despatch lists/shipping documents, schedule of bolts and nuts.

04.3.2 All drawing work shall be in metric system and preparation of drawings shall conform to iS:696 "Code of Practice for General Engineering Drawings", Symbols for welding shall conform to IS:813 "Scheme of Symbols for welding".

04.3.3 The fabrication drawings shall show full length layout with all connecting members, and connections, marked thereon. The fabrication drawings shall include all the necessary blown-up details required for the correct fabrication of the structure to meet the design requirements. These drawings shall be made in conformity with the best modern practices and with due regard to speed and economy in fabrication and erection. Each erection piece shall be clearly identified by an erection mark in these drawings. All the fabrication drawings shall, wherever specified, have the approval of the Engineer before commencement of fabrication. Approval of drawings will not absolve the Contractor from his responsibility for the correctness and completeness of shop drawings. The Contractor shall correct at his own expense all errors of any sort in his drawings and cover all damages due to such errors, regardless of any approval by the Engineer.

04.3.4 The preparation/detailing of fabrication drawing shall be complete in all respects. In the case of bolted connections, the bolt diameter, the hole diameter, the actual locations of bolt holes, co-ordinating scheme with connecting/matching elements shall be clearly indicated. Where HSFG Bolts are used, method of surface preparation shall be indicated.

04.3.5 In case of welded connections, the size and length of welds along the relevant weld lines shall be distinctly marked. The length specified shall be the effective length excluding end crates. For all butt-welds, details of appropriate edge preparation shall be indicated.

04.3.6 Detailing of structural steel members subjected to dynamic loading shall be such as to keep the stress concentration to a minimum. Cross-welding shall be avoided as far as practicable. Welding across tension flange of crane girders shall not be permitted.

For bolted connections subject to dynamic loading, a lock nut or spring washer in addition to plain washers shall be used.

04.3.7 Erection drawings may consist of line diagrams,showing every detailed member in position with the respective erection mark. Erection marks shall appear on the LEFT END of members AS DETAILED. All steel members shall be erected with marks in the same relative position as shown in plan or elevation. All loose members shall be either given part marks or wired on to the main erection mark for despatch.

04.3.8 The erection clearances for cleated ends of members connecting steel to steel should preferably be not greater than 1.5 mm at each end. The erection clearance at ends of beams without web cleats should not be more than 3 mm at each end but where for particular reasons greater clearance is necessary, suitably designed seatings shall be provided.

04.3.9 The fabrication drawings shall be prepared in such a manner that structures are despatched with maximum transportable length and work involved at site is minimum. Steelwork shall be shop-fitted and shop-assembled as far as practicable.

04.3.10 All edge preparations for welding shall conform to IS:9595 (latest).

04.4.0 MATERIALS

04.4.1 All steel and other materials used for steelwork and in association with steelwork shall conform to the specifications shown on the drawings or otherwise conform to appropriate Indian Standards. Only tested materials shall be used unless written authority is obtained for the use of untested materials for certain secondary structural members.

04.4.2 Structural steel shapes shall in general conform to IS:226(latest). In case of welded fabrication with mild steel, steel plates shall conform to IS:226(latest) or IS:2062(latest) according to suitability for welding. For tubular structures, steel tubes shall conform to IS:1161(latest).

04.4.3 Mild steel electrodes used for welding shall conform to IS:814 (latest) and as specified in the specification /drawing. For welding in any particular position the electrodes used shall be those recommended by the manufacturer for use in that position. The current used shall be as per electrode manufacturer's recommendations.

04.4.4 Black hexagonal bolts and nuts shall conform to IS:1363. Precision and turned hexagonal bolts and nuts shall conform to IS:1363. HSFG bolts, nuts and washers shall conform to IS:3757 Grades 8.8 and 10.9 or to ASTM specification A325 and A490 or equivalent or as approved by the Engineer.

04.4.5 Certified mill test reports of materials used in the work shall be made available for inspection by the Engineer upon request.

04.4.6 Approval for substitutions of structural steel sections shown in the design drawing must be obtained in writing from the Engineer. This will not normally be withheld in case of non-availability of design section. Payment for such authorised changes shall be made on the basis of sections actually used.

04.4.7 All materials shall be straight and if necessary before being worked shall be straightened and/or flattened by pressure including decoiling of plates unless required to be of curvilinear form and shall be free from twists.

04.4.8 For utilizing the cut pieces and available lengths,the Contractor may have to do full strength butt welded splices, at no extra cost to owner. The design and location of such splices shall require prior approval of the Owner. If plates/flats of required widths are not available, it will be necessary for the Contractor to cut such sizes at no extra cost to Owner.

04.5.0 STRUCTURAL STEEL CONNECTION

04.5.1 The Contractor shall be responsible for the design and detailing of all connections. The design of connections shall provide for adequate strength for the transfer of force in the structural elements indicated on the design drawings. For purposes of detailing the connections, the allowable stresses in material, bolts and welds shall be as per IS:800 and IS:816 or as specified in the design drawings.

04.5.2 Except where otherwise noted on the drawings, welding shall be used for all shop connections, as well as field connections. Connections other than those shown on the drawings,shall have prior approval of the Engineer.

04.5.3 For all full strength butt welding of plates and sections thicker than or equal to 10 mm.,edge preparation shall be done and got approved by the Engineer.

04.5.4 The use of ordinary bolts, HSFG bolts, shop and site welding shall be as indicated on the drawings unless approved otherwise by the Engineer.

04.5.5 Two numbers of washers shall be used for all bolted connections, one washer bearing against the head and other bearing against the nut.

04.5.6 The magnitude of forces shown on design drawings shall be used at face values with no reductions for connections.

04.5.7 All bracing shall have a nominal draw of 1 mm for each 1500 mm length.

04.5.8 Bracing shall be connected for 50% of the capacity of the member in tension (for single angle bracing member consider full area as effective) or the forces indicated on the drawings whichever is greater, unless otherwise noted.

04.5.9 Sliding, rolling, hanging or slotted hole connections as specified in the design drawing shall be designed to allow for necessary amount of movement at joints. Joints with slotted hole connection shall have slotted holes as specified on the design drawing. The bolts shall have two nuts, the outer being tightened against inner with a clearance of 2 mm between the inner nut and the connected material.

04.5.10 All penetration for piping, conduit, cable trays, etc., through grating or plate flooring shall be cut and suitably banded in the field, except when such penetrations are dimensioned in the drawings,in which case they shall be shop cut and banded.

04.6.0 FABRICATION & DELIVERY

04.6.1 Fabrication of all structural steelwork shall be in accordance with IS:800 (latest) unless otherwise specified, and in conformity with various clauses of this specification.

04.6.2 Wherever practicable and wherever perfect matching of parts is required at site, members shall be shop assembled before despatch to minimise site work. Parts not completely assembled in the shop shall be secured, to the extent possible, to prevent damage during despatch.

04.6.3 All pieces shall be properly identified and bundled for transportation to work site. Care shall be exercised in the delivery, handling and storage of material to ensure that material is not damaged in any manner. Materials shall be kept free of dirt, grease and foreign matter and shall be protected from corrosion. All materials shall be stored properly on skids above the ground which shall be kept clean and properly drained. Girders and beams shall be placed upright and stored. Long members such as columns and chord members shall be supported on skids placed near enough to prevent damage due to deflection.

04.6.4 Bolts shall be furnished according to bolt lists showing the location of their use and additional bolts shall be supplied to cover wastage.

04.6.5 All fabricated pieces shall bear erection mark numbers painted/punched according to appropriate erection and shop drawings at a prominent location on the structure for easy identification.

04.6.6 All workmanship shall be in accordance with the best practice in modern structural shops. Greatest accuracy shall be achieved in the manufacture of every part of the work and all identical parts shall be strictly interchangeable.

04.6.7 Templates used throughout the work shall be of steel/ steel bushed, in such cases as the Engineer may consider necessary. In cases where actual materials have been used as templates for drilling similar pieces the Engineer shall decide whether they are fit to be used as parts of the finished structures.

04.6.8 All smithy work shall be accurately made to the dimensions shown on the drawings and shall be clean and sound. The metal shall not be burnt or injured in any way. All joggles shall be formed by pressure. Crankedsections and knees may however be formed by cutting and welding unless otherwise indicated in the design drawings.

04.6.9 Shearing or flame cutting may be used at the Contractor's option provided that a mechanically controlled cutting torch is used for flame cutting and that the resulting edges are clean and straight. Unless clean square and true to shape all flame cut edges shall be planed/cleaned by chipping or grinding. Where machine flame cutting is permitted for high tensile steel, special care shall be taken to leave sufficient margin and all flame hardened material shall be removed by machining/edge planing.

04.6.10 Wherever shearing is used for cutting to size, sheared members shall be free from distortions at sheared edge.

04.6.11 The ends of all girder stiffeners shall be in contact with the compression flange and shall be planed or ground to fit tightly against flange plates unless otherwise stated on the drawings. Care shall be taken to ensure full bearing of the stiffeners at the supports by machining the contact surfaces of both bearing stiffeners and bearing plates. The ends shall not be drawn or caulked.

04.6.12 Column splices and butt joints of struts and compression members depending on contact for stress transmission shall be accurately machined and close-butted over the whole section with a clearance not exceeding 0.1 mm locally at any place. In column caps and bases. the ends of shafts together with the attached gussets, angles, channels etc., after welding together, should be accurately machined so that the parts connected butt over the entire surface of contact. Care should be taken that these connecting members are fixed with such accuracy that they are not reduced in thickness by machining by more than 1.0 mm. Where sufficient gussets and welds are providedto transmit the entire loading, the column end need not be machined.

04.6.13 Holes for permanent black bolts shall not be more than 1.5 mm larger than the nominal diameter of the black bolts unless specified otherwise. All holes for turned and fitted bolts shall be sub-punched or drilled and reamed at site under assembly of connected parts to a tolerance of plus 0.3mm unless specified otherwise.

04.6.14 Holes in purlins, side sheeting runners, packing plates and lacing bars may be punched full size. Holes in light framing with the exception of joint holes, may be punched full size.

04.6.15 All punching and sub-punching shall be clean and accurate and all drilling free from burrs. In block/batch drilling, parts shall be separated after drilling and the burrs removed.

04.6.16 No hole shall be made by gas cutting process.

04.6.17 The component parts shall be so assembled that they are neither twisted nor otherwise damaged and specified cambers, if any, shall be provided.

04.6.18 No drifting of hole shall be permitted except to draw the parts together. Drifts used shall not be larger than the nominal diameter of bolt. Drifting done during assembly shall not distort the metal or enlarge the holes.

04.6.19 Sufficient trial assembly shall be carried out in the fabrication works to prove the accuracy of workmanship and the number of such trials required will be at Inspector's discretion.

04.6.20 Where necessary, washers shall be tapered or otherwise suitably shaped to give the heads of bolts a satisfactory bearing.

04.6.21 The threaded portion of each bolt shall project through the nut at least one thread.

04.6.22 In all cases where the full bearing area of the bolt is to be developed, the bolt shall be provided with a washer of sufficient thickness under the nut so as to avoid any threaded portion of the bolt being within the thickness of the parts bolted together.

04.6.23 Ends of structural members and portions of gussets receiving welding at site shall be left unpainted.

04.6.24 The welding and the welded work shall conform to IS:816 and other relevant codes unless otherwise specified.

04.6.25 Welding shall be done by the electric arc process. Automatic welding shall be employed for important structures as specified in the drawings.

04.6.26 Generally, submerged arc, automatic & semi-automatic welding shall be employed. Only where it is not practicable, manual arc welding may be resorted to. In case of manual arc welding, recommendations of electrode manufacturer is to be strictly followed.

04.6.27. Welding shall not be done under such weather conditions which might adversely affect the efficiency of the welding and where necessary, effective protection or other safeguards shall be provided.

04.6.28 Only qualified welders suitable for the job shall be employed. The engineer at his discretion can order periodic tests in accordance with IS:817 of the welders and/or of the welds produced by them.

04.6.29 Welds shall be made using requisite jigs and fixtures to avoid distortion or damage to members during/after welding. Welds on exposed work shall be finished uniformly smooth to present a neat appearance.

04.6.30 As much work as possible shall be welded in shops and the layouts and sequence of the operations shall be arranged so as to eliminate distortion and shrinkage stress to the satisfaction of the Inspector.

04.6.31 Welding work shall be under constant supervision of competent welding supervisor and shall be done in a properly organised manner with the approved quality welding sets and with automatic welding machines. Details of welding procedure shall be agreed upon with the Engineer before fabrication is commenced.

04.6.32 Welding procedure shall include the following :-

i) Type and size of electrodes.

ii) Current and arc voltage.(for automatic welding)

iii) Length of run per electrode, or (for automatic welding) speed of travel.

iv) Number and arrangement of runs in multirun welds.

v) Position of welding.

vi) Preparation and set-up of parts.

vii) Welding sequence.

viii)Pre or post-heating.

ix) Any other relevant information.

04.6.33 The welding procedure shall be arranged to suit the details of the joints as indicated on the drawings and the positions in which the welding is to be carried out. The welds shall meet the requirements of quality specified.

04.6.34 All electrodes for use in the work to which this specification relates shall be kept under dry conditions. Electrodes which are damaged by moisture shall not be used unless it is stated by the manufacturer that when it is properly dried there will be no detrimental effect. Any electrode which has part of its flux coating broken away or is otherwise damaged shall be discarded.

04.6.35 The Contractor shall prepare the edges with an automatically controlled flame cutting torch followed by grinding correctly to the shape, size and dimensions of the groove, prescribed in the design and shop drawings. In case of U-groove joint, the edges shall be prepared with an automatic flame cutting torch in two passes following a bevel cut with a gouging pass, or by machining.

04.6.36 The welding surfaces shall be smooth, uniform and free from fins, tears, notches or any other defect which may adversely affect welding. The welding surfaces and the surrounding surfaces within 50 mm of weld shall be free of loose scale, slag, rust, grease, paint, moisture or any other foreign material.

04.6.37 Pre-bending of plates for three plate welded sections shall be done where found necessary.

04.6.38 Manipulators shall be used where necessary and shall be designed to facilitate welding and to ensure that all welds are easily accessible to the operators.

04.6.39 Where full strength butt-welds are specified, run-on and run-off pieces shall be used.

04.6.40 The welding shall be such that the face of weld deposit shall at all places be proud of the surfaces of the parent metal by 1 to 1.5 mm. Where a flush surface is required, the surplus weld metal shall be ground and dressed off.

04.6.41 After completing each run of weld, all slag shall be thoroughly removed, and the surface cleaned before starting the next run of weld.

04.6.42 Stress relieving after welding shall be done,if specifically called for in the drawing.

04.6.43 The weld metal, as deposited (including tack welds if to be incorporated) shall be free from cracks, slag inclusions, gross porosity, cavities and other deposition faults. The weld metal shall be properly fused with the parent metal without serious undercutting or over-lapping at the toes of the weld. The surfaces of the weld shall have a uniform and consistent contour and uniform appearance.

04.6.44 All weld runs found defective shall be cut by using either chipping hammer, gouging torch, or suitable grinding wheel in such a manner that adjacent material is not injured in any way.

04.6.45 Peeling of the welds involving deformation of the weld surface either during deslagging or thereafter shall not be allowed.

04.6.46 Column bases and caps, if applicable, shall be in one solid piece, and except when cut from plates with true surfaces, shall be accurately machined over the bearing surfaces, and shall be in effective contact over the whole area of the machined end of the stanchion.

04.6.47 Each piece shall be distinctly marked before delivery, in accordance with an approved marking diagram and shall bear such other marks as will facilitate erection. For easy identification at site,a small distinguishing mark for each building shall be painted at each end of every member before despatch from fabrication shop. The fabricated steelwork shall be despatched in sequence as per agreed programme and for such portion as may be found convenient for erection or as ordered by the Engineer.

04.6.48 The Contractor shall provide suitable packing wherever necessary to guard against damage during handling and transportation to site. All fabricated parts shall be adequately braced to prevent damage during transit.

04.6.49 The tolerances for fabrication of steel structures shall generally conform to IS:7215, unless otherwise specified in this specification or drawings. (Refer Table I to Table III).

04.6.50 Any fabrication or erection work which is considered not to be keeping with the Technical Specification forming the Contract, or in the absence of Technical Specification with recognised good practice, shall be rectified/replaced/corrected at the Contractor's expense as directed by Engineer.

04.6.51 Site fabrication work shall also conform to all specifications, stipulations, terms andconditions applicable for shop welded structures as mentioned above.

GOTO TOP                   GOTO DATABSE

 

Sign My Guest Book

View My Guest Book

Old Entries
GB-1 | GB-2 | GB-3 | GB-4

101 Manangement Tips ] CICC - Japan ] Free Book Review* ] Down Loads ] Current Projects ] Personal ] My Memoir ] Technical Data Bank ] Link Exchange ] Views of Visitors ] भोजपत्र देवनागरी  Hindi - Section ] [Bhojpuri Sansaar] [Global Database of Bhojpuri people] [Structural - World :: Design Centre]

See who's visiting this page. View Page Stats
See who's visiting this page.

This  web site has been   Created and Developed by Yrs. Truly (Binay Kr Pandey). The content of this site is totally personal and for information only. If you notice any anomaly,  misrepresentation of fact or incorrect detail, do E-mail to me so that it can be readily corrected. Created in May-2001 and being updated regularly. Last Update 28-June-2004.

The content of this site is shall not be copied without permission.

Dear Visitor, If you are not able to find what you have been looking for on this site, please do try your search once again with different combination of words in the following Google Tool Bar, Specially designed to provide enhanced search option. Thank you.

Google
1