1881-1885

s the Building Commission attempts to concentrate on completion of the building's exterior to avoid damage from the weather, disputes continue with Councils over inadequate funds and pressure to prepare more interior spaces for occupancy.

1881

Bldg 1881 Jan. 1881

May 1881


Oct. 1881
Dec. 1881

Councils provide $750,000 of $1,467,950 requested.
Offices are prepared for the City Treasurer, City Controller, City Commissioners, and Park Commissioners.
First electric lights turned on in building.
East and west center pavilions are completed to 4th floor.


1882

South elevation - 1882 Jan. 1882

Oct. 1882


Dec. 1882

Councils provide $750,000 for construction.

South exterior, including center and corner pavilions is completed.

Tower reaches 88 feet.


1883

NE corner - 1883 Jan. 1883
Aug. 1883

Dec. 1883

Councils provide $750,000 for construction.
Conversation Hall, the grand 5 story meeting room for Councils, is completed.
All exterior facades and roofs are complete except for north center and corner pavilions. Tower reaches 118 feet.


1884

Tower @196 ft - 1884 June 1884



Dec. 1884
Councils pressure for more completed interior offices, as work progresses on interior stairs and offices in southern end of building.

North roofs and pavilions completed. Tower reaches 196 feet.


1885

Dec. 1885 Work concentrated on internal systems, elevators, boilers, electric supply and water supply. Tower reaches 266 feet.