1876-1880

xcitement over the new City Hall seemed to wane near the end of the decade as Councils began a trend of shortchanging the Commission in its funding requests.

1876

1876 work stopped Mar. 1876

May 1876
Oct. 1876

Work is suspended when Councils fail to provide requested $1,193,250 funding appropriation.
Councils provide $500,000 and marble work continues.
Work begins on temporary space for occupancy by State Supreme Court.


1877

courtyard turret - 1877 Jan. 1877


Jun 1877

Oct. 1877

Commission requests $1,500,000. Councils provide NO FUNDING. State Supreme Court occupies temporary quarters on 2nd floor south side room 254.
Marble contractor must sue for payment as 1st story marblework is completed.
State Supreme Court reaffirms Building Commission authority and requires Councils to provide requested funding allocations.


1878

SW view of site 1878 Feb. 1878

Dec. 1878

Councils provide $600,000 of $1,217,400 request.

Marble work on eastern, western, and southern facades nears top of 2nd story.


1879

Jan. 1879


May 1879

July 1879

Councils provide $750,000 of $1,265,000 request and urge Commission to concentrate on preparation of more interior space for occupancy.
Studies begin for redesign of heating, ventilation, and water supply to incorporate latest technology.
Architect John McArthur expresses concern over weight of tower.


1880

Bldg - 1880 Jan. 1880

Dec. 1880

Councils provide $665,000 of $1,274,000 request.

Exterior marble facade is complete to 2nd story around entire building and 3rd story on south side. Work progressing on interior rooms as well.


1881 - 1885

[GO TO HOME PAGE] [NEXT PAGE]

1