March 1, 2003
Lighting and doorbell
Met lighting person at
the Brimfield model home. She had a computer program that
displayed all the available lighting choices. We pretty
much stayed with the standard lighting fixtures.
|
|
|
*** |
|
|
March 2, 2004
Flooring and countertops.
We visited WCCV in
Uniontown. Picked out wood flooring for the foyer, dinette,
and kitchen and vinyl for the bathrooms and laundry room.
The rest of the house will be carpeted (teal in master
bedroom, burgundy in living room, “pebble creek” [aka “tan”]
everywhere else. Picked out the kitchen and bathroom
countertops as well. That was the hard part. The vinyl
flooring samples are big—probably 2 foot square—and the
countertop samples are tiny—probably 1 inch by 2 inches.
|
|
|
*** |
|
|
March 9, 2004
Preconstruction.
Julie introduced us to
the Foundation Supervisor and the Project Manager. We made
a couple of changes to the plans and turned in our color
selections.
|
|
|
*** |
|
|
March 19, 2004
Closing!
Signing all the papers
was uneventful and took about an hour. The stressful part
was yesterday when the title company contacted us to tell us
what our closing costs would be. The company did not
initially credit us for the entire amount of our earnest
deposit. After that was corrected, everything was smooth
sailing. We drove out to our home site and found that the
Foundation Supervisor was already staking out the lot. That
was pretty neat to see. He also posted the building permit.
|
|
|
*** |
|
|
March 29,
2004
DIGGING
BEGINS.
Contractor
began
digging
about
8:00am.
By 9:30am
they had
finished
hooking up
the sewer,
water, and
gas.
The basement
was dug by
about
2:00pm.
|
|
|
*** |
|
|
March 31, 2004
Foundation.
The foundation was poured for the entire house. The drain
system for the basement was also installed. |
|
|
*** |
|
|
April 2, 2004
Concrete Block, Part 1
The concrete block, sand, and concrete mix were delivered today.
The brick for the band around the front of the house was also
delivered. |
|
|
*** |
|
|
April 7, 2004
Concrete Block, Part 2
About one half of the concrete block work was finished today.
We also met one of our new next-door neighbors. She and
her husband have five school-aged kids!
|
|
|
*** |
|
|
April 8, 2004
Concrete Block, Part 3
The basement and garage block work is pretty much finished.
There are only 1 or 2 rows left to finish in the garage.
The stoop is mostly finished as well. Before the block was
in, the hole didn't seem as if it was deep enough for the
basement. But now that the block is in, it definitely
looks deeper.
|
|
|
*** |
|
|
April 9, 2004
Concrete Block, Part 4
The basement and garage block are finished, as well as the
stoop. The brick band was put around the front of the
foundation. A nice touch that we didn't know they were
going to do was they put a smooth coat of cement over the top
few rows of block to create a more finished look. We were
surprised and happy about that.
|
|
|
*** |
|
|
April 12, 2004
Waterproofing
The waterproofing or the basement was completed today.
|
|
|
*** |
|
|
April 14, 2004
Back Fill
Dirt was back filled against basement walls and a 4' layer of
stone was placed on top of that.
|
|
|
*** |
|
|
April 23, 2004
Back Fill 2
Completed the back fill of the basement and the garage.
Grade was smoothed for majority of yard and steel beam and
support poles for the basement were delivered. Basement
has about 4" or 5" of water in it. Either that means the
basement is so waterproof on the outside that the water has no
place to go or we will have an indoor swimming pool for free.
|
|
|
*** |
|
|
April 26, 2004
Materials & Floor
The lumber was delivered today. Pam, Rena, and Kari went
to visit the site with us. When we got there we saw the
workers installing floor joists. We left for a little
while and by the time we returned, the decking had been
installed.
|
|
|
*** |
|
|
April 27, 2004
Framing
Framing of main floor and garage completed today. Crew
started to lay the plywood for the second floor.
|
|
|
*** |
|
|
April 28, 2004
Framing 2, Bath tubs & Showers
Rough framing was finished on the second floor today. Bath
tubs and showers were delivered to be lifted to second floor
for installation before roof trusses and sheeting are put in place.
|
|
|
*** |
|
|
April 29, 2004
Framing 3, Windows & Doors
Framing is complete. Roof and front peak installed.
The windows, doors, and sliding glass door were delivered today.
|
|
|
*** |
|
|
April 30, 2004
Framing 4, Windows & Doors
The windows, sidelights, and doors were
installed today. The cornices above the front windows were
also installed. We were happy to see that the workers
picked up all of the scrap in the yard and threw it in the giant
Dumpster that is in the driveway. That left the yard
fairly tidy. We ate our first meal at the house too.
Our food of choice? Pizza!
|
|
|
*** |
|
|
May 3, 2004
Plumbing
The plumbers started to work on the plumbing. All of the
holes and cut outs were made for the piping and the PVC for the
drains was delivered. The shingles were also delivered
today and should be in place soon. We were finally able to
go into our basement. The 12 inches plus of water were
finally pumped out.
|
|
|
*** |
|
|
May 4, 2004
Plumbing 2
Drain pipes were hooked up in entire house today. The
water lines were installed in the upstairs bedrooms. The
tubs and showers were also installed today. Sump pump was
installed and the main electrical was run to the house as well
as the gas main line.
|
|
|
*** |
|
|
May 5, 2004
Heating, Electrical
The heating/air conditioning ducts were installed on the second
floor. The electrician was in and installed all of the
outlet and switch boxes and has started to run the electrical
wire on the second floor. The fire place was delivered
today. It is all boxed up so were unable to see what it
looks like.
|
|
|
*** |
|
|
May 6, 2004
Electrical 2
The electricians have spent another day installing the wiring.
It appeared that most of the wire has been run, it needs to be
hooked up to the electrical box. The plumbers were in
sometime today and charged all of the waste water lines and
copper pipe to check for leaks. The fireplace was also
installed today. The shingles are on now. They had
the main part of the house done by noon.
|
|
|
*** |
|
|
May 7, 2004
Electrical 3
The electrical rough in was completed today.
|
|
|
*** |
|
|
May 10, 2004
Concrete
We went out to the house today expecting to find at least a
start on the siding. Much to our surprise we found the
concrete had been poured for the front stoop, garage, and
basement. That was okay with us as we are putting up
insulation in the garage this weekend and it would have been a
challenge with the ladders with the very uneven dirt that was in
the garage.
|
|
|
*** |
|
|
May 12, 2004
Garage Door
We arrived at the house today to clean up some of the brush in
the back yard. After about 15 minutes of looking around we
noticed a lot of nails on the garage floor. Finally we
looked up and found we had a garage door.
|
|
|
*** |
|
|
May 14, 2004
Insulation, Siding
Today was an extremely long, but rewarding day. The day
started with us going to Scott's former boss to borrow his truck
to pick up the insulation for the garage. When we arrive
at the house at about 9:45 the workers had a major part of the
siding started. We let them work and came to the house
around 2:30 and found the house completely sided and everyone
gone. We were very pleased with the outcome! From
then we began insulating. Around 3:30 Mark Stauffer, one
of Scott's friends from the airport and one of our neighbors
arrived to help with the insulation. By 5:30 we had the
entire garage walls and ceiling insulated. It was a lot of
work but we are glad it's done.
|
|
|
*** |
|
|
May 17, 2004
Insulation
The insulation was installed downstairs and upstairs in
preparation for the drywall installation this week. The
yard was graded again to even it out.
|
|
|
*** |
|
|
May 20, 2004
Drywall
The drywall and joint compound were delivered today.
|
|
|
*** |
|
|
May 24, 2004
Spouting, Drywall 2
The gutters and downspouts were installed today. The
drywall was also installed today. The joints have not been
filled in yet.
|
|
|
*** |
|
|
May 25, 2004
Downspout lines, Drywall 3
The lines that hook the downspouts, sump pump, and garage floor
drain were all hooked up to the sewer system today. The
workers began the taping and mudding of the walls today.
We found out today that they have until June 2 to finish.
We received an update on the schedule of things to come:
-
June 3 - Wall priming begins,
electrician begins final electrical work, cabinets and trim
are delivered.
-
June 7 - Trim is hung and cabinets
installed.
-
June 11 - Countertop laminate
installed.
|
|
|
*** |
|
|
June 2, 2004
Drywall 4, Attic Insulation
The drywall was finished today as well as the knock down texture
on the ceilings. When we arrived, workers were blowing
insulation into the attic and finished that.
|
|
|
*** |
|
|
June 4, 2004
Painting, Staining & Electrical
The walls throughout the house were primed
today. All of the exterior doors were painted both inside
and out as well. All of the wood trim was delivered and
stained as well as the spindles and railings for the stairs.
We also had all of the interior doors delivered and the screens
for the windows were delivered too. The electrician was
back and installed all of the sockets and light switches and
finished hooking up all of them to the electrical box. |
|
|
*** |
|
|
June 7, 2004
Floor, Trim
Today the carpenters began to set up for the finish work.
The trim was all cut to length, the walls were marked for the
cabinets, and the sub-floor was put in for the vinyl and wood
floors.
|
|
|
*** |
|
|
June 8, 2004
Trim, Doors, Railings & Furnace
The interior doors in all of the rooms were installed upstairs
today. All of the doors and windows were trimmed as well
upstairs. The hand rail was installed for the stairs to
the second floor and the stairs to the basement. They also
began to install the railing in the office that will separate it
from the stairwell.
|
|
|
*** |
|
|
June 9, 2004
Trim, Doors & Railings 2
The rest of the interior doors were hung today and the trim work
was completed except the areas of the floor where the vinyl
floor and wood floor need to be installed.
|
|
|
*** |
|
|
June 10, 2004
Furnace
The furnace was set in place today and the heat ducts were run.
|
|
|
*** |
|
|
June 14, 2004
Cabinets
The kitchen and bathroom cabinets were delivered today.
|
|
|
*** |
|
|
June 15, 2004
Cabinets 2
The kitchen and bathroom cabinets were installed today. We
took some measurements to see if our selections for
appliances will fit. While most of them should be okay, we
had to make some changes in our selections.
|
|
|
*** |
|
|
June 16, 2004
Countertops
The Formica countertops were installed in the kitchen and the
master bathroom and full bathroom upstairs.
|
|
|
*** |
|
|
June 17, 2004
After some more careful considerations, and a "wonderful" scale
model I (Scott) made, we found that one of our appliances
(microwave/hood combo) would fit after all. We were
worried about the clearance between the range and hood. It
turns out it will work out very well.
|
|
|
*** |
|
|
June 18, 2004
Painting, Staining
The wood trim and stair rails were stained and sprayed with a
polyurethane to protect it.
|
|
|
*** |
|
|
June 21, 2004
Plumbing
The rest of the plumbing was roughed in on the first floor and
the hot water heater was installed. The hot water heater
ended up being the wrong size (10 gallons too small) so they
will have to take it out and put the right size in.
|
|
|
*** |
|
|
June 23, 2004
Flooring
The vinyl floor and hardwood floor were delivered today.
Installation should begin tomorrow.
|
|
|
*** |
|
|
June 24, 2004
Flooring, Light fixtures & Doorknobs
The wood floor and vinyl floor were installed today. They
all turned out very well. The light fixtures were
delivered. According to the packing list, one of the
fixtures we chose is on back order. The doorknobs and door
pulls were installed on all of the doors.
|
|
|
*** |
|
|
June 25, 2004
Hot water heater, Electrical & Plumbing
The hot water heater was replaced with the correct size.
The electricians started the final installations. They
hooked up the rest of the outlets and switches and installed the
face plates. The eye ball lights above the fire place, the
lights in the garage, and a light in one of the extra bedrooms
were installed. The smoke/carbon monoxide detectors were
hooked up. They are hooked together so that if one goes
off, they all will go off (5 in total). All of the sinks
and toilets were delivered. The sink in the master
bathroom was installed.
|
|
|
*** |
|
|
June 28, 2004
Fireplace, Light fixtures
The stone work was installed around the fireplace. All of
the light fixtures that are not on back order (2 of them) were
installed throughout the house.
|
|
|
*** |
|
|
June 29, 2004
Plumbing
All of the sinks were installed. The toilet in the half
bath was installed. The other two bathrooms' toilets were
not installed. We are not sure if they ordered the wrong
ones, there were 3 delivered earlier. The water spigot to
the garage was installed and the garbage disposal was hooked up.
|
|
|
*** |
|
|
July 1, 2004
Plumbing, Closet shelves & Painting
The plumbing was completed today. The rest of the toilets
were installed and the water line for the refrigerator was
installed. All of the shelving in the closet were
installed. Another coat of paint was put on and some of
the dirt and saw dust was cleaned up.
|
|
|
*** |
|
|
July 2, 2004
Carpet, Yard
The carpet installers began the process of installing the
carpet. The tack strips were installed in all of the rooms
and the padding was also installed in all of the rooms.
The dirt in the back yard was removed and smoothed out.
|
|
|
*** |
|
|
July 6, 2004
Carpet
The carpet was installed in all of the rooms. The final
cleaning has been scheduled for July 13. After that are
the inspections and we will be able to move in.
|
|
|
*** |
|
|
July 7, 2004
Registers, Air conditioner
The air conditioner, registers, and thermostat were installed
today. Some of the items left to do are mirrors in
bathrooms, garage door opener, driveway, sidewalk and final
painting.
|
|
|
*** |
|
|
July 12, 2004
Garage door, Driveway & Final carpentry
The garage door opener was installed today. The driveway
and sidewalks were prepared for concrete pour. The mirrors
in the bathrooms were installed and the shower doors were
installed in the bathroom.
|
|
|
*** |
|
|
July 13, 2004
Final cleaning, Light fixtures
The final cleaning was completed today. All of the windows
were washed, carpets vacuumed, garage and basement floor washed,
and bathroom tubs and showers cleaned. The remaining light
fixtures that were on back order were installed as well.
The only item to complete is the concrete in the driveway and
sidewalk and a final grade.
|
|
|
*** |
|
|
July 14, 2004
Driveway, Sidewalk
The driveway and sidewalk were poured today. With that,
construction is DONE! The builder will come in and grade
next to the sidewalk and driveway. Now we wait for the
final inspections and we will be ready to move in.
|
|
|
*** |
|
|
July 26, 2004
Final walk through
We met with the construction supervisor today and went over the
operation of some of the items in the house and pointed out some
small issues we had that we wished to have fixed. We are
scheduled to close this Friday as long as the occupancy
certificate can be completed.
|
|
|
*** |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|