OK, I am building a new house and the links below should be a dated order of events
Click on the photos to get to that page
My first house. Nothing special, but it was cheap and I was broke. Not too bad of a shack for a couple of years. Gave me enough time to do the following-
Date- 4/17/03
Things are winding down, but there are a few items to deal with. Starting to set stuff up, so take a look at some of that...
LIGHTING!
check out the light fixtures if that is your thing...
Date- 3/6/03
Things upstairs are just about done. Siding is up, my stuff is moving in...
Date- 1/29/03
paint, flooring. Things are a little slow. Trying to put the heat to the contractor.
Date- 12/20/02
Drywall hung, mud is next, then paint, then cabinets, then carpet, then me moving in.....
Date- 12/8/02
another month gone by and there are a few things done- drywall is soon. Finish date set for 1/31/03- let's watch that date slide.....
Date- 11/6/02
Wow, it's almost a month later.....
Date- 10/17/02
Roof is almost done.
Date- 10/1/02
Things are getting built.
Date- 9/15/02
Walls poured- finally! Things should be moving quick from here.
Date- 8/26/02
Footings poured. Walls should be up by the end of the week.
Date- 8/19/02
Hole dug. Getting ready to lay out the footings. Things should start moving quick from here.
Date- 8/12/02
Lot is cleared from trees. 1.25 acres total with most of the trees left. The area you will see should be for house only +30' around.
1