STRATA ENGINEERING CONSULTANTS LTD.

 

 

 

 

 

 

 

LANDSLIDE INVESTIGATION

AT

BLACK MALLET/MAYNARD HILL

CASTRIES, ST. LUCIA, WEST INDIES

 

 

 

 

 

 

 

P.O.BOX GM931, Bellevue Estate, Gros Islet, St. Lucia, West Indies

Telephone: (758) 450-0872 Facsimile: (758) 452-6092 e-mail: geostrata@hotmail.com

 


 

CONTENTS

1.0 INTRODUCTION

2.0 TOPOGRAPHY AND DRAINAGE

3.0 REGIONAL GEOLOGY

4.0 SEISMIC CONSIDERATIONS

5.0 FIELD INVESTIGATION

5.1 General

5.2 Standpipe piezometer (SP) Installation

5.3 Slope Inclinometer (SI) Installation

6.0 LABORATORY PROCEDURES

7.0 SUBSOIL CONDITIONS

7.1 General

7.2 Colluvium

7.3 Sand

7.4 Bedrock-Highly weathered Andesite

8.0 LIQUIFACTION POTENTIAL

8.1 Statement of the Problem

8.2 Applications to Black Mallet/Maynard Hill Landslide

9.0 HYDROLOGY AND HYDROGEOLOGY

10.0 INSTRUMENTATION MONITORING

10.1 Standpipe Piezonieters

10.2 Slope Inclinometers

11.0 SLOPE STABILITY ANALYSIS

12.0 DISCUSSIONS AND RECOMMENDATIONS

12.1 General

12.2 Causes of Slope Failure

12.3 Remedial Slope Stabilisation Measures

12.3.1 Slope Drainage

12.3.2 Design of a Stabilising Toe Berm

12.3.3 Depressurization of the Confined Sand Aquifer

12.3.4 Reinforced Passive Piles

12.3.5 Ground Bio-Engineering

13.0 INSPECTION AND SUPERVISION

APPENDIX A - Borehole Logs

APPENDIX B - Grain Size Distribution Curves

APPENDIX C - Atterberg Limits Tests Results

APPENDIX D - Direct Shear Strength Tests Results

APPENDIX E - Slope Inclinometer Data

APPENDIX F - Slope Stability Data

APPENDIX G - Design of Stabilising Toe Berm

PHOTOGRAPHS

DRAWING

1.0 INTRODUCTION

The problem of the stability of the slope at Black Mallet/Maynard Hill in the southeast of Castries was brought to public attention with dramatic force in early October, 1999 when approximately 80,000 cubic metres of colluvial material 'flowed' downslope toward the Marchand River, resulting in the destruction of several concrete structures and ruptured public utilities serving the community. Residents of tl-le community reported that minor cracks were observed developing on masonry walls and concrete floor slabs during the last week of September, 1999. On October 5, the Ministry of Communications, Works & Public Utilities were notified of these disturbing developments by a resident.

On October 9, 1999 a team of government officials led by the Minister of Communications, Works and Public Utilities, the Honourable Calixte George and a few consulting engineers, including the author, made a walk-over of the site to assess the damage caused by the earth movements. At the time of the visit, tension cracks were observed on the Black Mallet and Maynard Hill roads and across the slope in an East - West alignment. Several concrete structures showed evidence of distress and water mains were ruptured.

On completion of the site visit, a meeting was held in the Minister's office to discuss a plan of action to address the problem. The author was assigned the responsibility to identify the extent of the slide area and to list the number of buildings and residents affected. A total of 300 persons and approximately 60 residences were identified as being affected by the landslide. On October 11, 1999 a meeting was called by the Prime Minister, the Honourable Kenny Anthony to discuss the events at the Black Mallet/Maynard Hill site. At this meeting, the Prime Minister assigned the author the task to investigate and report on the landslide event.

This report contains the results of the investigation together with discussions and recommendations for remedial slope stabilisation measures.

2.0 TOPOGRAPHY AND DRAINAGE

 

The community of Black M allet/Mapiard Hill is located at the southeast corner of the city of Castries at the toe of the North Slope of Morne Fortune. The slide area is bordered to the north by the Marchand river, a tributary which meanders northward into the main Castries river. The natural course of the Marchand river is controlled by the geologic structure of the sediments along its banks. In the slide area, the river has actively downcut the embankment deposits and recent test borings and excavations identify andesite bedrock to be approximately 1.5 in below riverbed elevation. At various places along the banks the river has left deposits of colluvial material comprised of slit, sand, gravel and boulders. These deposits were actively being downcut by the river during periods of flooding and in some areas, form steep unstable slopes.

The right (north) abutment slope (looking downstream) is relatively flat, while the left (south) slope is steeper, generally greater than 15 degrees and rises southward toward the communities of Black Mallet and Maynard Hill to elevations of 25 in and 60 in, respectively. On the left slope, a drainage ditch has deeply incised into the colluvium and surface water has ponded in a small depression at the toe of the ditch.

Tension cracks are prevalent on the left slope and are considered to be due to differential movement within the slide area, There is a well defined scarp up to 1.5 in high, approximately 80 in upslope from the river. The landslide colluvium is mainly clayey silt and sand, with cobbles and boulders exposed on the ground surface.

To the west of Maynard Hill, the ground rises steeply to approximately 140 in elevation with a crest at Parker Hill where highly weathered andesite bedrock outcrops at some locations. The Marchand river meanders southward and forms the eastern boundary of the site. The vegetal cover at the slip site is mainly horticultural and agricultural. Dense tropical forests flourish on the east slope of Parker Hill overlooking the site.

The Marchand River is the main drainage watercourse for the site area. Surfice run off from Maynard Hill and Parker Hill flows into the Marchand River via a limited number of road drains, but large volumes flow indiscriminately over the ground surface at the site during periods of high intensity rainfall. To the cast of Parker Hill, Ravine Touterelle flows northward from the crest of Morne Fortune to merge with the Marchand River at the toe of the slope at Black Mallet.

During the site investigation programme, ponded water was observed in shallow depressions at a few locations on the slope. Residents have claimed that the immediate area between SP99-BM-1 and SP99-BM-2 remains saturated with surface water during the wet and dry months of the year. The author is of the opinion that this is due to leaking septic tanks and the indiscriminate disposal of waste water by residence.

3.0 REGIONAL GEOLOGY

The Antillean arc of Caribbean islands is geologically young, probably not exceeding 50 million years and is predominantly of volcanic origin. In general, the islands were formed by the accumulation of lava flows and volcanic ash deposits, initially on the seabed, followed by seabed uplift. During the gradual uplifting process the emerging islands were colonised by coral caps and after emergence, coastal reefs developed.

There is abundant evidence of volcanic activity at eight sites within the arc, including hot springs, sulphurous streams, gas vents, near surface hydrothermal hot spots and recent lava and ash eruptions at Soufriere-Montserrat and Soufriere-St. Vincent.

St. Lucia and the associated undersea ridge on which it is perched are located approximately 150 kilometers from the east ridge of the Caribbean Plate where it meets the North American Plate which passes down into the mantle where melting occurs. Earthquake and volcanic activity in the St, Lucia area is related to the subduction process.

St. Lucia is almost entirely volcanic with the oldest rocks, largely rhyolites, andesite and andesite porphyry and various basalt lavas, dating from the Early Tertiary period of about 50 million years ago. These older rocks are found at the surface in the extreme northern parts of the island and probably underly the most recent rocks found elsewhere.

Approximately 25 million years ago, there was a period of general submergence of the entire Lesser Antilles and during this period there was a development of coral reefs which were later uplifted above sea level. Along the coast there are beds of mixed sedimentary and volcanic materials with well developed bedding w-id stratification. Most beach sands are a mixture are a mixture of calcareous coral and shell fragments and particles derived from the volcanic rocks.

4.0 SEISMIC CONSIDERATIONS

The design basis earthquake (DBE) would be an event with an annual probability of exceedence of 0.0021, which is equivalent to a 10 % chance of exceedence during a 50year period. Determination of a maximum credible ground motion is often done deterministically, rather than probabilistically. In order to estimate the ground motion at this site, a suitable distance-attenuation relationship is required. To date, there has not been sufficient strong motion data recorded to allow a regional attenuation relationship to be developed. Therefore, relationships developed for other parts of the world have been used to estimate a range of possible values for peak ground acceleration. The predicted peak horizontal ground acceleration ranges from 10% to 37% depending on the magnitude and the attenuation law assumed. The mean value is 23%.

In addition, calculated values for ground acceleration for the two most recent recorded earthquakes felt in St. Lucia have been noted. The 1953 earthquake was located at 14 degrees N, 61 degrees W by the United States Geological Survey (USGS), and 14.1 degrees N, 61.2 degrees W by Sykes and Ewing (1965). The 1946 earthquake was reported by Gutenberg and Richter (1954) at 14.5 degrees N, 60.5 degrees W. The peak ground acceleration in St. Lucia estimated for these two events lie in the range of 5 % and 14 %, depending on the attenuation relationship assumed.

TABLE 4.1

Seismic Record of Saint Lucia 1997/1999

YEAR

MONTH/

DATE

HOUR/

MINUTE

SECOND

LAT.

LONG.

DEPTH

MAG

 

1997

17-Mar

0537

26.46

+14.19

-60.48

60

 

E of SLU

1997

4-Aug

0401

00.99

+14.09

-61.13

26

3.3

N/E SLU

1997

24-Aug

1127

 

+14.54

-60.56

97

3.9

N/E Martinique

1997

29-Aug

1947

23.42

+14.00

-60.78

29

2.1

E of SLU

1997

13-Sep

1852

19.51

+13.84

-61.04

1

 

SLU (volcanic)

1997

13-Sep

1916

14.48

+13.84

-61.04

1

 

SLU (volcanic)

1997

13-Sep

1917

45.04

+13.53

-60.67

5

2.9

S/E SLU

1997

21-Sep

1938

20.62

+13.19

-60.17

35

3.3

E of SLU

1997

27-Sep

1547

31.86

+14.23

-58.18

35

4.2

Far E of SLU

1997

27-Sep

1555

07.91

+14.12

-58.26

35

4.5

Far E of SLU

1997

27-Sep

1559

19.76

+14.20

-58.29

83

4.2

Far E of SLU

1997

28-Sep

1405

42.00

+14.23

-58.22

42

4.0

Far E of SLU

1998

19-Sep

         

5.0

 

1999

19-Feb

0758

 

+54.76

-37.02

47

3.9

E of SLU

1999

6-Apr

1703

 

+15.06

-60.29

27

3.9

N/E of SLU

1999

29-May

   

+28.55

-47.54

25

2.9

 

1999

8-Jun

0803

 

+14.56

-60.28

27.4

5.0

N/E Martinique

1999

3-Jul

0507

 

+59.06

-28.71

26

4.3

 

1999

11-Jul

0751

 

+19.85

-6.09

10

4.9

 

1999

3-Oct

0250

 

+46.41

-1.51

3

2.5

 

1999

13-Nov

2115

 

+40.51

-24.63

32

3.2

 

Five pointed stars on this diagram are seismograph stations, with three or four letter codes. These are black on the original. Six pointed stars are earthquakes. On the original these are colored wither red indicating shallow focal point or blue indicating depths greater than 30 km. The smallest stars are earthquakes of magnitude less than 3 and biggest is an earthquake, which occurred on June 8 1999 with the following properties.

Time of occurrence: 08:04 Eastern Caribbean Time

Epicentral location: 15.017E N. 60.31.4EW

Focal Depth: 3 5 KM

Magnitude: 5.7

This location is 100 – 125 km from Saint Lucia.

The great majority of the historical and recorded earthquakes used in the probabilistic analysis of the DBE were tectonic earthquakes. There have been some earthquakes in the region associated with volcanic activity and eruptions, for example on Dominica and Montserrat. Earthquakes of this type can do a great deal of damage, but their effects are generally confined to a local area, thought usually to be less than 2 kilometers in radius. Robson (1964) does attribute a long series of small earthquakes felt in St. Lucia in 1906 to this type of earthquake (Shepherd).

For the pseudo-static analysis of the stability of the slope at Black Mallet, a more empirical approach is adopted, as recommended by Seed (1979). In a pseudo-static method of analysis the effects of an earthquake on a potential slide mass are represented by an equivalent static horizontal force determined as the product of a seismic coefficient 'g,' and the weight of the potential sliding mass. The numerical value of 'g' depends on the intensity of the earthquake. Freeman (1932) proposes the follow values for 'g':

Severe earthquakes, Rossi-Forel scale IX g = 0.1

Violent, destructive, Rossi-Forel scale X g = 0.25

Catastrophic g = 0.5

Professor Seed (1979,1983) has stated that virtually any virtually any earthen structure can withstand moderate earthquake shaking with peak accelerations of about 0.2g with no detrimental effects.

Table 4.1 contains a record of seismic events in St. Lucia front 1997 to 1999 as reported by the office of Disaster Preparedness. During the period of June to November 1999, five earthquakes of magnitudes ranging from 5.0 to 2.5 have been reported. Also attached is an insert of additional seismic data on St. Lucia from the Seismic Research Unit of the University of the West Indies, St. Augustine, Trinidad.

5.0 FIELD INVESTIGATION

5.1 General

The field investigation is the central and decisive part of a study of landslides and landslide prone areas. The investigation serves two essential purposes, namely:

i) to identify areas subject to sliding when future construction is being planned and

ii) to define features of and environmental factors involved in an existing slide.

Unstable areas prone to sliding usually exhibit symptoms of past movement and incipient failure; most of these can be identified in a field investigation before design. Such investigations can show how to prevent or at least minimise future movements mid they can suggest alternative areas that are less likely to slide. Ideally, field investigations should commence long before construction is anticipated and sometimes continue long after the area has been changed by the anticipated construction.

A number of features require study in a field investigation including:

    1. topography
    2. geology
    3. groundwater regime
    4. weather conditions
    5. history of slope alterations

 

5.2 Standpipe Piezometer (SP) Installation

The subsurface exploration program at Black Mallet commenced on October 18th, and was completed on November 30th. 1999. Five piezometer boreholes (SP99-BM-1 to SP99-BM-5) were drilled to depths varying from 6.0 m to 8.25 m below existing ground surface at selected locations within the movement zone, utilizing hollow stem augers attached to a track-mounted, DHM-163R drill rig with a motorised cathead. A 75 mm diameter tri-cone drill bit was used to penetrate rock fragments and boulders encountered during the subsurface exploration program.

Standard Penetration Tests (SPT) were conducted at regular intervals of depth in all the boreholes in accordance with ASTM D1586. To perform this test, a spoon sampler is lowered down the borehole until it rests on the layer of soil to be tested. It is then driven into the soil for a length of 450 mm by means of a 65 kg weight hammer free falling 760 mm for each blow. The number of blows required to drive the last 300 mm is recorded and this figure is designated the 'N'-Value of the soil, The first 150 mm of driving is ignored because of possible loose soil in the bottom of the borehole from the boring operations. After the sampler has been removed from the borehole it is opened and its contents examined. The recovered disturbed soil samples were visually classified in the field, placed in plastic bags and scaled to retain their natural moisture content.

Three undisturbed shelby tube samples were recovered at selected depths in the piezometer (SP) boreholes. Hollow stem augers and a tri-cone drill bit were used to advance the boreholes to the required sampling dept. A 75 min diameter hollow, metal "shelby" tube is then fitted to drill rods attached on ends and lowered through the hollow stem auger and pushed into the soil with the drilling head to recover the undisturbed sample. A pocket penetrometer was utilised in the field to determine the unconfined compressive strength of the subsoils.

On completion of drilling, a perforated, 38 mm diameter plastic PVC standpipe piezometer was installed in the five borcholes to monitor groundwater levels and to conduct hydraulic conductivity tests. In boreholes SP99-BM-1 and SP99-BM-2, the tip of the piezometers were located at mid-height of the sand layer. SP99-BM-3 to SP99-BM-5 piezometers were installed with their tips located 1.5 in above the base of the colluvial material.

The piezometer installations were conducted as follows:

The borehole was backfilled with auger cuttings up to the base of the soil layer to be tested. Bentonite pellets were soaked in diesel fuel to retard their reaction with water and were lowered down the borehole to form a 0.5 m thick seat at the base of the layer.

The lower 3.0 m length of the PVC plastic pipe was slotted, at 150 mm intervals with a hacksaw and a scaled end lowered to the selected elevation in the borehole by adding 6.0 m lengths of plastic pipe connected on ends by couplings and sealed with PVC adhesive. The borehole was then backfilled to within 2.0 m of ground surface with 12 mm diameter clean, crushed rock placed around the piezometer. A betitonite/cement slurry was used to top the upper 2.0 m of the borehole to form an impermeable seal to prevent the ingress of surface water into the piezometer. A cap was placed over the protruding end of the standpipe piezometer and is removed when recording groundwater levels.

5.3 Slope Inclinometer (SI) Installation

The slope inclinometer is a device used for monitoring deformation normal to the axis of a casing by means of a probe passing along the casing. It is used to determine the extent, rate and zone of landslide movement.

The slope inclinometer system has four components:

    1. A permanently installed guide made of plastic and contains longitudinal grooves or slots for orientation of the sensor unit
    2. A portable probe containing a gravity-sensing transducer, which is mounted in a carriage designed for operation in the guide casing
    3. A portable control readout unit at the surface supplies power, receives electrical signals and displays readings in digital format
    4. A graduated electrical cable linking the probe to the readout unit and is raised or lowered in the casing and transmits electrical signals to the surface

The plastic casing used for this project is of 70 mm diameter and 3.0 m lengths and is made of an ABS (acrylonitrite/butadiene/styrene) compound. The casing is manufactured with aligning grooves for controlling the orientation of the probe and are joined together with rigid couplings.

Five boreholes (SI99-BM-1 to S199-BM-5) were drilled to depths ranging from 6.5m to 11.0m for slope inclinometer installation. The boreholes were drilled approximately 1.5 m distance from the piezometer locations to observe any correlation between groundwater fluctuations and subsurface movement.

The plastic slope inclinometer casing sections were layed out and couplings marked to show location of the alignment key. A bottom cap was placed at one end of the first section, sealed with ABS cement and taped to prevent soil or grout from entering the casing. The remainder of the casing was assembled by adding on sections connected with couplings and scaled with ABS cement. During the installation process, the axis of one pair of grooves was kept parallel to the anticipated direction of movement i.e. downslope. The orientation was maintained throughout the installation process. A grout slurry composed of Portland cement, bentonite and water was used to backfill the borehole and to provide stability to the casing.

The slope inclinometer casing was installed in vertical boreholes, which pass through a zone of suspected movement. The bottom of the casing was anchored in stable ground and serves as a reference. The inclinometer probe was used to survey the casing and establish its initial position.

Detailed borehole logs are included in Appendix A.

The locations of the boreholes are shown on the attached topographic drawing.

6.0 LABORATORY PROCEDURES

The recovered disturbed and undisturbed soil samples were placed in plastic bags in the field and scaled to retain their natural moisture content. The disturbed samples were utilised in our laboratory to determine insitu moisture content, grain size distribution, Atterberg limits and to confirm the field classification of the subsoils. Three undisturbed shelby tube samples were packaged and transported by air to Trintoplan Consultants Ltd. in Trinidad for shear strength testing in their laboratory. The results of the shear strength tests are as follows:

Borehole No.

Material

Depth

Unit Weight

Effective cohesion

Angle of Internal Friction

Source

       

peak

residual

peak

residual

 

SP99BM1

Colluvium

5.8

18.00

37.5

20.0

9.0

6.0

Trintoplan

SP99BM2

Colluvium

5.5

17.95

11.0

4.4

5.5

4.5

Trintoplan

SP99BM4

Colluvium

2.2

18.10

17.3

14.0

15.0

6.0

Trintoplan

Natural moisture contents are plotted on the borehole logs in Appendix A.

Grain Size Distribution Curves are included in Appendix B.

Atterberg Limits Test results are shown in Appendix C.

Direct Shear Test results data is in Appendix D.

7.0 SUBSOIL CONDITIONS

7.1 General

The general subsoil stratigrapily at the site consists of colluvial material overlying highly weathered andesite bedrock. A sand deposit exists between the colluvium and bedrock at the location of boreholes SP99-BM-1 and SP99-BM-2 and may represent an old river deposit was not encountered in the channel which was buried by the colluvium. The sand deposit was not encountered in the borcholes located upslope to the east, west and south of the site. The tip of the standpipe piezometers installed in boreholes SP99-BM-1 and SP99-BM-2 were located in the sand material and the piezometers showed water level readings indicative of artesian pressure from a confined aquifer.

7.2 Colluvium

Colluvium is defined as any soil deposit which has moved downstope to its present position by a mass wasting process such as creep, slope wash, erosion or landslide. This material was encountered in all the boreholes at this site. It consists of boulders and cobbles within a sandy, clayey silt matrix. The stratum ranges in thickness from 4.0 m in boreholes SP99-BM-3 and SP99-BM-4 to 6.0 in boreholes SP99-BM-2 and S199-BM-5. Most values for the natural moisture content of tl-ils material ranged from 12 to 36

The higher values were found in samples containing a high clay content. The results of Atterberg limits performed on selected samples ranged from 34 % to 71 % depending on the clay content of the sample. The plasticity charts show that this deposit has a low to medium plasticity due the presence of a large amount of sand. A few values fall above the upper portion of the 'A' line indicating a material of high plasticity. Based on the plasticity charts this colluvial deposit may be described generally as a sandy, clayey inorganic silt of low to medium plasticity, Atterberg limits results are in Appendix C.

The grain size distribution curves are contained in Appendix B. The material is generally well graded with 14 to 39% sand.

The 'N'-values from the Standard Penetration Test ranged from 2 blows to 46 blows per 0.3m indicative of a soft to very stiff material. The 'N'-value generally increases with depth. Standard Penetration Test (N-values) are included on the borehole logs.

7.3 Sand

In boreholes SP99-BM-1, SP99-BM-2 and S199-BM-1 a sand deposit was encountered in a confined aquifer under hydrostatic pressure. The sand layer ranges in thickness from 2.0 in to 4.25 in. A sand sample was recovered at a depth of 3.0 -4.0 m below the riverbed at the toe of the failed slope during the excavation for placement of the rock toe berm.

The field moisture content of this material ranged from 14 to 26.7 % The sand is well graded with a mineral content of rock fragments, quartz and feldspars. Grain size distribution curves are in Appendix B.

The 'N' values from the Standard Penetration Test ranged from 10 blows to 44 blows per 0.3m. The dense values were from boreholes SP99-BM-1 and S199-BM-1 located in close proximity to the Marchand River where a drainage path was available for dewatering of the sand grains. Upslope at the location of borehole SP99-BM-2 the sand is loose and is confined under hydrostatic pressure.

7.4 Bedrock - Highly Weathered Andesite

The following weathering classification scheme proposed by Anon (1972) was found to be workable for the weathered rocks in the tropics. The terminology applied to the bedrock material description is as follows:

TERM

DEFINITION

GRADE

Fresh

Parent rock showing no discolouration, loss of strength or any weathering defects

W1

Slightly Weathered

Rock may be slightly discoloured, particularly adjacent to discontinuities which may be open and will have slightly discoloured surfaces; the intact rock is not noticeably weaker than the fresh rock

W11

Moderately Weathered

Rock is discoloured: discontinuities may be open and will have discoloured surfaces with alterations starting to penetrate inwards: intact rock is noticeably weaker than the fresh rock as determined in the field.

W111

Highly Weathered

Rock is discoloured: discontinuities may be open and will have discoloured surfaces and the original fabric of the rock near to the discontinuities may be altered. Alteration penetrates deeply inwards, but corestones are still present.

W1V

Completely Weathered

Rock is discoloured and changed to a sol, but original fabric is mainly preserved. There may be occasional small corestones. The properties of the soil depends in part on the nature of the parent rock.

WV

Residual Soil

Rock is discoloured and completely changed to a soil in which the original rock fabric is completely destroyed.

WV1

The highly weathered andesite rock encountered beneath the sand deposit at this site is very dense and contains corestones.

8.0 LIQUIFACTION POTENTIAL

8.1 Statement of the Problem

The term "liquefaction" as used in this report is defined as follows:

Liquefaction - is a phenomenon wherein a mass of soil loses a large percentage of its shear resistance when subjected to undrained monotonic, cyclic or shock, loading, and flows in a manner resembling a liquid until the shear stresses acting on the mass are as low as the reduced shear resistance.

The loss in shear resistance is due to the conversion of the mass from a practically drained condition, at which it can sustain the in situ shear stresses to a practically undrained condition of shear.

Liquefaction can occur in saturated sands, silts and "quick" clays and can also occur in very large masses of sands or silts that are dry and loose enough so that the air cannot escape from the voids fast enough to prevent undrained shear. This section of the report deals only with liquefaction of saturated sands as that which exist at the Black Mallet – Maynard Hill landslide site.

If a slope or embankment composed of saturated sands or silts fails due to liquefaction, the soil mass comes to rest only after the slope is reduced to few degrees and the shear stresses have consequently been reduced to the mobilised shear resistance. Because of the rapid movement, very large displacement and the fluid-like behaviour of the soil associated with these types of slope failures warrants the term "flow slide" used to describe them.

Soils sheared to large strains eventually reach a 'steady state' of deformation. Poulous (1971) presented the following definition of the 'steady state' of deformation:

The 'steady state' of deformation for any mass of particles is that state in which the mass is continuously deforming at constant volume, constant informal effective stress, constant shear stress and constant velocity. The 'steady state' of deformation is achieved only after all particle orientation has reached a statistically steady-state condition and after all particle breakage, if any, is complete so that the shear stress needed to continue deformation and the velocity of deformation remain constant.

Liquefaction, as defined above, involves large unidirectional shear deformations, and thus one would expect trial during liquefaction failures the soil will tend towards the ‘steady state' of deformation, If the shear strength at the 'steady state' is lower than the applied shear stress in the ground, then, in principle, it is possible for liquefaction to occur. Conversely, if the 'steady state' shear strength is greater than the shear stress in the ground, then liquefaction cannot occur because the associated large unidirectional deformations are not possible.

A careful examination of the definition of Iiquefaction stated above indicates the following two explicit conditions:

    1. Liquefaction involves large, unidirectional shear deformations, which usually occur at a relatively rapid rate when failure occurs in situ so that it appears to be flowing.
    2. Liquefaction requires the presence of 'driving' shear stresses significantly greater than the shear strength of the soiI after the loss of shear resistance. These driving shear stresses supply the driving force which produces the large and rapid, continuous deformation.

8.2 APPLICATIONS TO BLACK MALLET – MAYNARD HILL LANDSLIDE

One of the most common index properties for estimating liquefaction strength is the SPT N-value obtained from the Standard Penetration Test. This test is intended to measure the number of blows delivered by a 64 kg weight hammer dropped 760 mm in a free fall required to drive a 50 mm diameter (O.D.) sampler 300 mm into the ground. The reasons for using SPT-N values in most liquefaction evaluations are summarized below:

The sand layer beneath the colluvium deposit at Black Mallet-Maynard Hill is in a loose, saturated condition with a pore water pressure ratio (ru) of 0.25. Slope inclinometers installed in this deposit show large strain movements of 6 cm/day at the sand/bedrock interphase. This large rate of movement can be interpreted as the result of shear stresses being greater than the shear strength in the ground resulting in liquefaction of the sand deposit.

9.0 HYDROLOGY AND HYDROGEOLOGY

St. Lucia has a tropical climate with an average daily temperature of about 27 degrees Celcius, Average annual rainfall varies from 1500-mm in the drier coastal zones to 4500mm mm in the central mountains. A dry season extends from January to June and a wet season from July to December. The seasons are not always distinct, however, and rainfall can be variable. Typically, 30 % to 40 % of the rainfall occurs during the dry season. Very wet months can occur in the dry season and dry months can occur during the wet season. The high interior of the island receives the most rainfall with a high proportion of this being orographic. With the central water-divide being closer to the west than the east coasts and this distance being only 8-9 km, rainfall on the west coast tends to be higher than that on the east coast. The island lies in the hurricane belt and in the past has suffered from extreme high winds and torrential rains during August to October.

The data for the hydrology studies included long-term monthly precipitation data from Government House at Morne Fortune and at George V Park in Castries. For all stations rainfall is consistently higher for the latter six months of the year. Mean monthly maxima vary from 190 mm to 430 mm between the different stations.

The George V Park and Government House stations are the closest to the site. RainfalI recorded for 1999 are as follows:

 

 

George V Park

Government House

Month

mm

mm

Jan

141.7

142.8

Feb

59.5

50.2

Mar

50.4

49.3

Apr

94.2

82.5

May

25.7

18.3

Jun

115.5

105.0

Jul

190.9

201.1

Aug

302.1

327.5

Sept

216.5

203.4

Oct

212.9

195.4

Nov

226.9

201.0

 

Static groundwater levels were measured in boreholes SP99-BM-1 to SP99-BM-5 at depths of 4.1 in 3.0m, 3.5m, 3.5m, 5.5m below existing ground surface, respectively. The water table follows the slope geometry with flow occurring northward and eastward towards the Marchand River.

It should be noted that groundwater levels at the site would be subject to seasonal variation and could be significantly higher during flooding periods of the Marchand River. However, the drilling program was carried out during the wet season and thus, the groundwater levels taken at that time are likely to be at the higher end of the range.

The hydraulic conductivity (k) of the colluvium and sand was measured as specified by the United States of America Department of the Navy, Naval Facilities Engineering Command - 1974 (NAVFAC), for a cased hole with a perforated extension of length 'L'.

The expression used is:

 

R^ 2

L

h1

k =

1n

1n

 
 

2L(t2-t1)

R

h2

where,

k mean hydraulic conductivity

R radius of standpipe piezometer (19 mm)

L = length of perforated staiidpipe (3.0m)

h1 = piezometer head for t = t 1 mm; t2 – t1 ( 3600 seconds)

h2 = piezometer head for t = t2 mm

t = time, seconds

Hydraulic conductivity tests were conducted in all of the standpipes installed at the site.

The test procedure used was as follows:

1) The standpipes were filled with water and allowed to dissipate overnight.

2) The standpipes were again filled with water the following day and the drop in water level was monitored as follows:

The results of the hydraulic conductivity tests are as follows:

 

Borehole No.

Depth (in)

Description

Hydraulic Conductivity {cm/sec(-1)}

SP99-BM-1

6.5

sand

2.8 x 10(-4)

SP99-BM-2

7.0

sand

4.3 x 10(-3)

SP99-BM-3

3.0

colluvitim

1.4 x 10(-6)

SP99-BM-4

3.5

colluvitim

3.7 x 10(-5)

SP99-BM-5

4.0

colluvitim

1.1 x 10(-6)

10.0 INSTRUMENTATION MONITORING

10.1 Standpipe Piezometers

A knowledge of excess pore (ground) water pressure conditions is required for calculation of the factor of safety of a slope. The measurement of excess pore water pressure within a saturated zone is most commonly carried out using piezometers installed in boreholes. The time taken for the piezometer to respond to a change in pore pressure in the ground should be sufficiently short to give a meaningful accurate measure of the actual pore pressure. The response time will depend on the rate of change of groundwater pressures due to seasonal rainfall and individual storm events and the accuracy required. Due to the various factors within the hydrological cycle that affect groundwater flows, and hence piezometric levels, a wide range of piezometric responses can be anticipated. The principle ways in which piezometers may respond to rainfall can be considered as either:

i) a storm response, being short term - hours to days

ii) a seasonal response, being longer term - months to years, or

iii) a combination of both effects.

 

Therefore, by monitoring piezometric responses over a period of time it may be possible to estimate likely responses to particular design storm events that could be expected within the design period being considered. The estimate would be based on the assumption that piezometric response is proportional to total rainfall but with due regard to factors such as storm duration, distribution of rainfall during the storm, antecedent groundwater conditions, timing of the storm relative to seasonal fluctuations. Such monitoring provides the first stem in obtaining data necessary for slope stability analysis. Long term groundwater level records would allow a reliable estimate to be made of the effect of pore water pressure fluctuations on the stability of slopes.

The piezometric levels recorded below existing ground surface following the installation of the piezometers are as follows:

 

Borehole No.

Depth (M)

Initial Piezometric level (m)

(30/10/99)

Current Piezometric level (m)

(5/12/99)

SP99-BM-1

6.5

3.0

4.1 (pinched at 5.6m)

SP99-BM-2

7.0

3.0

Dry (pinched at 3.9m)

SP99-BM-3

3.0

5.5

3.5

SP99-BM-4

3.5

2.0

3.5 (pinched at 2.5 m) (destroyed)

SP99-BM-5

4.0

5.2 (1/12/99)

5.2

10.2 Slope Inclinometers

The slope inclinometer provides useful quantitative information by defining the level of maximum lateral movement. It provides the most definitive early warning system of all impending slope failure in comparison with other forms of instrumentation. Ground movement causes the slope inclinometer casing to move from its initial position to a new position. The rate, depth and the magnitude of this displacement is calculated by comparing data from the initial survey to data from subsequent surveys. The inclinometer probe measures the tilt of the casing, which is converted to a lateral distance. Deviation from an interval is called incremental displacement and the sum of the deviations is called cumulative displacement.

The inclinometer probe, control cable and readout unit are used to survey the casing. The probe measures the inclination or tilt of the casing. The inclination is measured by two force-balanced servo-accelerometers. One accelerometer measures the tilt in the plane of the inclinometer wheels (the 'A') axis. The other accelerometer measures tilt in the vertical plane perpendicular to the wheels. (the 'B') axis.

During the survey, the probe is drawn upwards from the bottom of the casing to the top. it is halted at half meter intervals for inclination measurement ( two-foot intervals are used for English probes). To eliminate offset errors, the probe is drawn through the casing twice. On the second pass, the probe is rotated 180 degrees. During data reduction, the 0 and 180 degrees data are merged.

The Digitilt DataMate is a compact inclinometer readout that records data from the inclinometer probe, The DataMate stores over 10,000 data points in up to forty sets. The DataMate Manager software (DMM) creates a project database that holds records of inclinometer installations and data from inclinometer surveys. The data is transferred from the DataMate to the project database on the computer and is used and is used to generate simple graphs of displacement.

The result s of the inclinometer surveys carries out at Black Mallet are included on the next few pages. An explanation of the calculation in the report is warranted. For example, for slope inclinometer installation SI99-BM-1, the incremental displacement at 7.9 m (26.0 ft).

 

Incremental displacement

=

Deviation (current) - Deviation (initial)

 

=

2.4714 inches - 1.1844 inches

 

=

1.2870 inches (32.7 min)

Cumulative displacement depth (n)

=

D1 + D2 + ....Dn

 

=

0.048 + (-0.1734) + .....+ 1.2970

 

=

1.5589 inches (39.6 mm)

Slope inclinometer data is included in Appendix E.

See Photographs Nos. 13-15; 19 & 20.

11.0 SLOPE STABILITY ANALYSIS

The Limit Equilibrium method for slope stability analysis was used in this design to determine the magnitude of the factor of safety. When a slope has failed, the factor of safety is unity and the analysis can then be used to estimate the average shearing resistance along the failure surface. The factor of safety is that factor by which the shear strength parameters may be reduced in order to bring the slope into a state of limiting equilibrium along a given slip surface.

A commercially available computerized model 'G-SLOPE' developed by Mitre Software Corporation of Edmonton, Alberta, Canada was used to perform back-analyses of the failed slope (cross-section 'A-A') and in the design of slope remedial stabilisation works. Three sections (A-A'; B-B'; and C-C') were selected to perform effective stress stability analyses on the failed slope. The analyses utillsed the simplified Janbu limit equilibrium method of slices for an irregular slip surface. A potential slip surface is selected and the potential sliding mass is divided into a number of vertical slices and the stability of each slice is considered in turn, on the assumption that the factor of safety for each slice is equal to the factor of safety of each of the others. Each slice is acted upon by its own weight, which produces shearing and normal forces on its vertical boundaries and shearing and normal forces along its base. The shearing and normal forces acting on the vertical boundaries depend on the stress-deformation characteristics of the material comprising the sliding mass.

The factor of safety 'FS' of a slope Is usually defined as the ratio of available shear strength to shear stress on the critical surface. The factor of safety in the simplified Janbu method is expressed by the following equation:

FS = f {[ c'b + (W - ub) tan O'] [ 1/cos m]}

W tan

Where,

FS = Factor of Safety

f = correction factor for internal forces

c = cohesion

b = width of the slice

W = weight of material within the slice

U = pore water pressure

O = effective angle of internal friction

= angle between total normal force acting on base of slice and the vertical in

m = stability coefficient

 

The back-analysis performed at section A - A' on the failed slope was to determine the shear strength of the soil mass at failure. In order to conduct this exercise, the technique applied involved analysing the original slope geometry and piezometric levels before failure and working backwards by altering the shear strength parameters of the subsoils until a factor of safety of unity is achieved. A value of zero cohesion was assumed for the saturated silty sand layer and for the partially saturated colluvium. The results of the back-analys is show the shear strength of the sand layer at failure was 0 = 21.0 degrees.

Partially saturated colluvial or tropical residual soils develop excessive negative pore water pressure (soil-suction) during the dry season which helps to maintain stability. During heavy successive rainfalls negative pore water pressure is reduced dramatically as rapid infiltration occurs resulting in a reduction of shear strength of the overlying colluvial material and failure generally occurs.

A 1.0 in thick soil layer was used in the analyses to represent the equivalent surgharge applied by buildings on the slope.

The three cross-sections chosen for stability analyses were as follows:

Cross-Section A.- A’

This section is the most critical and is located on the northern area of the slide where the sand aquifer was encountered and where slope movement was initiated in close proximity of the Marchand river. It represents the steepest slope at the site and the most unfavourable geological conditions concerning soil liquefaction. The sand deposit is the most critical soil layer controlling stability. The section with detailed geology is shown in Figures 1 - 5.

The stability of composit slip surfaces was performed through the sand layer moving on the bedrock surface.

Cross-Section B - B'

Located through the middle of the slide, this section also intersects the edge of the liquefied sand layer and compositional critical surfaces through the sand was analysed. The section with detailed geology is shown in Figures 6 & 7.

Cross-Section C - C'

This section is located on the southern edge of the slide where the sand layer is not present and composit critical surfaces are through the colluvium moving on the bedrock surface. The section and detailed geology are shown in Figures 8 & 9.

The following soil parameters were utillsed in the effective stress analyses:

Material

Unit Wt.

Effective Cohesion C’

Effective Friction angle O’

 

(kN/m^ 3)

(kPa)

(degrees)

Surcharge

18.0

0.0

9.0

Colluvium

18.0

0.0

9.0

Sand

20.0

0.0

27.0

Bedrock

-1 (infinitely strong)

   

 

Table 10 summarises the results of the stability analyses on the three selected cross-sections.

TABLE 10.1

SUMMEY of Slope Stability Analyses

 

Figure No.

Section

Slope Geometry

Seismic Coefficient

Factor of

Safety

Remarks

1

A - A'

Back analysis

0.0

1.02

Critical surface through loose sand

2

A - A'

Before excavation

0.0

1.29

Critical surface through loose sand

3

A - A'

Before excavation

0.03

1.12

Critical surface through loose sand

4

A - A'

After 1.5m

excavation

0.0

1.24

Critical surface through loose sand

5

A - A'

After 1.5m

excavation

0.03

1.07

Critical surface through loose sand

6

B - B'

No excavation

0.0

1.29

Critical surface through loose sand

7

B - B'

No excavation

0.03

1.12

Critical surface through loose sand

8

C-C’

No excavation

0.0

1.22

Critical surface through loose colluvium

9

C-C’

No excavation

0.03

0.99

Critical surface through loose colluvium

12.0 DISCUSSIONS AND RECOMMENDATIONS

12.1 General

Documented information on land degradation due to landslides in St. Lucia is contained in a few published and unpublished reports, including DeGraff, 1985; DeGraff et al, 1989 and Prior and Ho, 1972. The historical record of tropical storms and hurricanes, which have affected the island of St. Lucia from 1938 to the present, suggests that during this period there were at least thirteen major landslide-producing storm events on the island. In addition to these, landslides invariably develop on an annual basis during the rainy season or during high-rainfall periods of non-storm years. The high frequency and widespread distribution of these slope failures are evidence that landsliding is a dominant erosional process on the island.

Several types of landslides have been documented, including debris flows, debris slides, rock falls, rock slides and landslide complexes. Of the several landslide types, debris flows are the most common and are the main contributor to land degradation. These flows occur in soil or weathered rock, are typically small in size, and are initiated as shallow failures in the upper regions of tl-ie slope. The failed material, saturated with water becomes mobilised, flows downslope and carves deep erosion channels. Debris flows also erode the upper slopes of road bed, leading to the collapse of several road foundations. The significant volume of soil and other landslide debris carried by these flows to streams result in increase sedimentation of rivers and contribute to flooding downstream.

12.2 Causes of the Slope Failure

The Black Mallet/Mayiiard Hill slope has been in a 'steady state' of deformation or creep for a period of years as evidenced by old cracks observed in several concrete structures in the area. Soil creep (slow gravitational movement of the surface soils) appears to occur virtually throughout the study area. Although individual movements have been small, cumulative deflection over a period of time may have affected the performance of the slope. Creep is usually a forewarning of active instability that may be initiated by uncontrolled events. This is supported by a stability analysis conducted for the original slope prior to construction activity and a factor of safety of 1.29 (Figure 2) was calculated which is indicative of an unstable slope.

The construction of the river wall at the toe of the slope required the excavation of approximately 1.5 m width of material on the south bank of the river. A stability analysis performed for the slope after the excavation produced a factor of safety of 1.24 (Figure 4) representing a continuing 'steady state' of deformation.

Colluvial slopes are generally of limiting or marginal stability because over geological times the formation of a colluvial slope is a dynamic process, which naturally involves slope movement with gravity and water.

Factors which contributed to the landsliding at Black Mallet/Maynard Hill were:

- poor drainage facilities available to divert uphill surface run-off away from the site.

- the use of on-site septic disposal systems on most of the house sites.

- the build-up of hydrostatic pressure in the confined sand aquifer.

- the presence of loose, liquefiable sand in the aquifer

- the low shear strength charactistics of the colluvium

- seismic events prior to and at the time of the landslide are the main contributing factors which triggered slope failure. Table 4.1 indicates a seismic event occurring on October3, 1999 at the time of the occurrence of the landslide. The factor of safety of the slope prior to the excavation as stated above was 1.29. With a horizontal ground acceleration of 0.03g of the earthquake event, the factor of safety was reduced to 1.12 (Figure 7) which is marginal for stability. The factor of safety after the 1.5m width excavation at the toe of the slope was 1.24.This value was reduced to 1.07 (Figure 5) also marginal, for the same seismic event.

The failure of the slope at Black Mallet/ Maynard Hill slope was triggered by the liquifaction of the loose, saturated sand layer as a result of the earthquake event, which occurred during early October, 1999.

Karl Terzaghl's (1942) concept of slope stability are specifically expressed in the following words: "Theoretically, a factor of safety (FS) of 1.0 would mean a slide but in reality a slope may remain stable in spite of FS being smaller than 1.0 and it may fall at a factor of safety greater than 1.0, depending on the character of the slope forming materials." This statement clearly indicates that in Terzaghi's opinion a slope may be stable or unstable even if the computed factor of safety is greater than 1.0.

12.3 Progressive Failure

The initial failure of the slope at Black Mallet/Maynard Hill has since extended uphill by a progressive mechanism. Residents have reported the appearance of tension cracks around and within their houses. A well defined tension crack can be observed approximately 48 in upslope from the initial scarp.

When the toe of a large slope has failed, the removal of this toe support induces failure of the remaining slope. This can happen even when in entire slope has a factor of safety with respect to residual strength in excess of unity as long as some portion, usually the toe, has a factor of safety of less than 1.0. The initial failure occurs and reduces the stability of the slope that remains; then failure regresses until a region where the factor of safety is in excess of 1.0.

12.4 Remedial Slope Stabilisation Measures

12.4.1 General

Generally, stabilisation involves some or all of the following:

The control of subsurface water forms a major component of slope stabilisation works and is often the most efficient method of stabilisation. The details of the methods adopted to stabilise any particular slope depend on and can be severely limited by many factors including:

12.4.2 Slope Drainage

The control of surface water is most important in the stabilisation of slopes and should form part of any stabilisation program. Control of surface water consists of two parts;

The water collected must then be discharged in such a way that it does not affect the stability of adjacent areas. Efforts should be made to identify the source of recharge to the sand layer at the toe of the slide at Black Malley and every attempt should be made to divert surface run-off from Parker Hill eastward to Ravine Touterrelle. Once installed, drains must be maintained in proper working condition.

The existing road drains at Black Mallet and Maynard Hill are poorly constructed and should be replaced with properly designed open drains capable of containing run-off flows. The volume of water to be collected depends on rainfall intensity, and duration and catchment characteristics such as slope geometry, area and surface coverings. The volume should be determined in accordance with local engineering practice.

12.4.3 Design of a Stabilising Toe Berm

During the site investigation work at the site, the accelerated slope movement of 65.0 mm a ay warranted the immediate design and construction of a stabilising rock berm at the toe of the slope to arrest slope movement. Mr. Thomas Walcott, a consulting Engineer assisted the author by designing the toe berm, using soil parameters obtained from the field classification of the subsoils and the results of the instrumentation montioring.

The stabilising berm was constructed by excavating that portion of the Marchand river at the toe of the slope to bedrock at a depth of 1.5 in below the river bed and backfilling the excavation with boulders up to 2.0 m in diameter. The berm was 5.0 in high with a 6.5 m wide base.

Details of the stabilising toe berm are included in Appendix G.

12.4.4 Depressurization of the Confined Sand Aquifer

Lowering of the groundwater table in the confined sand aquifer by well pumping is an effective remedial measure for slope stabilisation at this site. A pumping test is required initially to determine the hydraulic characteristics of the aquifer and to provide information about the yield and drawdown of the well. In a well test, water is pumped during a certain time and at a certain rate. The effect of this pumping on the water table is measured in the pumped well and in some piezometers in the vicinity. The hydraulic characteristics of the aquifer is then found by substituting the drawdowns measured in the piezometers, their distance from the pumped well and the well discharge in an appropriate formula.

The well diameter must be selected so as to satisfy two requirements:

i) to accommodate the pump with proper clearance for installation and efficient operation,

ii) to assure hydraulic efficiency of the well

Piezometers are required in the well design to measure the effect of the pumping on the water table in the vicinity. A minimum of two piezometers are recommended for this site. The piezometers shall be located at specified locations in the field at a selected distance from the well based on the capacity of the pump used.

12.4.5 Reinforced Passive Piles

Piles installed through an unstable soil mass and into immobile bedrock beneath the failure surface can be used to arrest the movement of the failed soil mass. The use of I passive piles offers a technique that permits the installation of the stabilising system without potentially reducing the stability of the slope (as is required for wall construction).

Rowe and Poulos (1979) concluded that:

The recommended piles for this project shall be 450 mm diameter, bored cast - in - place reinforced concrete piles at a 1.5 m staggered spacing. Pile lengths shall be from 10.0 in to 12.0 in and they shall be installed with at least one third of their length into the weathered bedrock.

A set of three rows of staggered piles shall be installed along Maynard Hill and another installed on Black Mallet road and shall extend uphill to incorporate areas, which show evidence of instability.

Concrete for piling shall be high strength 5 100 psi mix and cubes shall be taken for laboratory testing. The contractor shall provide facilities for testing the integrity of each pile after installation.

Stability analyses on Section A - A' and C - C' with the reinforcing piles installed were performed using a seismic coefficient of 0.20. The calculated factors of safety were 1.65 and 4.63 respectively (Figures 10 & 11).

12.4.6 Ground Bio-Engineering

12.4.6.1 General

The removal of the natural vegetation on slopes has been identified by the author as the single most important misuse of land contributing to the erosion problem in St. Lucia; both surface wash and a greater risk of massive earth movements (landslides, debris flows etc.) being involved. The worsening of the erosion and land slippage problems can thus be closely correlated with the expansion of farming and residences on marginally stable slopes at the expense of forest cover.

Forest cover provides the following advantages to slope stabilisation:

    1. foliage intercepts rainfall, causing absorptive and evaporative losses that reduce rainfall available for infiltration into the soil
    2. roots extract moisture from the soil which is lost to the atmosphere via transpiration, leading to lower pore water pressures developing and a lower water table
    3. roots reinforce the soil, increasing soil shear strength
    4. tree roots may anchor into firm strata, providing support to the upslope soil mantle through buttressing and arching
    5. roots bind soil particles at the ground surface, reducing susceptibility to erosion

Selected species of natural tropical vegetation have been used on a limited basis by land owners for several decades in St. Lucia to assist in the control of soil erosion and slope stability along road cuts, steep slopes and river banks. The most common plant species used locally include : Glyricidia sepium (Glory Cedar); Bambusa vulgaris (Bamboo); Hibiscus pernambucinsis (Mahoemang); Hibiscus elatus (Blue mahoe); Mangifera itidica (Mango); Cecropla pelata (Bois canon); Vertivieria zlzaniodes (Vertiver grass).

Past study of landslides on St. Lucia shows approximately 2 percent of the land area of the island is disturbed by landslide activity (DeGraff et al, 1989). Since the onset of Tropical Storm 'Debbie' in October, 1994, and the resulting devastation caused by extensive landmass wasting from landslides and surface erosion mainly in cultivated and rural residential areas, there has been all urgent need to address the problem of slope stability and to seek solutions that will be beneficial to landowners, residents and the environment.

The existing landslide scars and tension cracks on the slope at Black Mallet/Maynard Hill will be subjected to further erosion from rainfall eroding material from the exposed soil surface. Appropriate surface stabilisation techniques would control the detachment of exposed soil particles and their migration from the scar area. The protection of the bare scar area from direct impact of rainfall and the force of running water across it will be necessary.

It is recommended that a ground bio-engineering program be included in the remedial slope stabilisation works at Black Mallet/Maynard Hill. The program shall include the planting of live poles of Blue mahoe, Species of mango; Bamboo; Mahoemang and Vertiver grass. The following are general specifications to be used for this program:

12.4.5.2 Specifications for the Preparation of Slope Prior to Planting

The objective of preparing the slope for planting is to ensure that the vegetation has a chance of becoming established. Vegetation needs to be protected from minor slope failures and slumps.

The following steps are necessary in slope preparation:

 

12.4.5.3 Specifications for Live Pole Planting

12.4.5.4 Specifications for Planting Live Cuttings

12.4.5.5 Specification for Planting Vertiver Grass

 

The planting of grasses on slopes is intended to create a strengthened slope surface that is resistant to soil erosion. The following are recommendations for successful planting of Vertiver grass:

13.0 INSPECTION AND SUPERVISION

It is recommended that a representative of Strata Engineering Consultants Ltd be called to inspect and supervise the dewatering programme and to monitor the piling and ground bio-engineering installations.

Should subsoils or subsoil conditions other than those described in this report be encountered during the remedial stabilisation works or if additional information pertinent to this project become available at some future date, the recommendations contained in this report may be altered or modified by the undersigned.

 

Respectfully submitted,

STRATA ENGINEERING CONSULTANTS LTD

Signed Roosevelt A. Isaac MSc., P.Eng.,

Executive Director

December 21, 1999


You are visitor since January 8, 2000
http://lucianstuff.i.am/
1