SEPTEMBER 11, 1997 MEMBERSHIP MEETING |
Field Trip Summary: |
On Thursday, September 11, 1997, the Corpus Christi Branch of ASCE took a Field Trip to the Lake Texana to Corpus Christi Pipeline. After meeting at the parking lot of Krieder's BBQ, on the west side of Hwy. 77 on the south side of Odem, about 35 ASCE members followed Gary Meurer, P.E., Project Manager with the Port of Corpus Christi Authority, to the project site near Sinton for a brief narrative on the construction of the pipeline and the status of the project. |
Mr. Meurer presented the following facts about the Water Pipeline: |
Contracts Awarded:
General Pipeline Construction |
Pate and Pate Enterprises |
$72,978,400 |
Purchase of Pump and Motors |
Patterson Pump Co. |
$856,320 |
Purchase of Motor Control Equipment |
Benshaw, Inc. |
$394,000 |
Construction of Pumping Plants 1 and 2 |
J.C. Evans Construction |
$8,325,000 |
Open Cut River Crossings |
Zaval-Tex Construction |
$5,598,406 |
Directionally Drilled River Crossings |
Michels Pipeline |
$3,887,720 |
Work Completed to Date:(September 1997)
Pipe Manufactured |
38.5 miles |
Pipe Delivered |
23.9 miles |
Pipe Installed |
9.5 miles |
Pipe Manufacturing Rate |
14,000ft/week |
Foundation work is also ongoing at all three pumping plants |