SUBMARINE BASE PILINGS
- Application of 100% Solids Polyurethane
Coatings
A 100% solids polyurethane coating dramatically outperformed a coal tar
epoxy system in protecting steel pilings at the Trident submarine base in King's Bay,
Georgia over a 5 year period. This case history does not involve tanks but does involve a
direct comparison between 100% solids polyurethane and epoxy over an extended period under
rather severe service.
During the spring of 1986, the U.S. Navy commenced the construction of its new Trident
submarine base. The program involved 200,000 square feet of steel pilings and a similar
quantity of pipe pilings. The pilings were coated with a 100% solids polyurethane and the
pipe pilings were protected with coal tar epoxy. Both coating systems met the Navy
specification 68-81-3020 Sec. 098505. No cathodic protection was used. The pilings were
coated by Pennsylvania applicator in the spring of 1986 and installed by South Carolina
construction company that fall.
Forty per cent of the pilings supported a permanent infrastructure of docks and piers. The
remaining pilings were used to construct a temporary dry-dock facility for use over 5 year
period for the rehabilitation of submarines. As part of the Navy's plan, these pilings
were removed during the summer of 1990 and scheduled for disposal. During the removal it
was discovered that the pilings coated with the polyurethane were in such pristine
condition that they could be re-used or sold for a future project. Further inspection of
the permanent pilings protected with the 100% solids polyurethane showed that they too
were in excellent condition.
The polyurethane exhibited no flaking, brittleness, cracking or delamination after 5 years
of abrasion, salt spray and tidal activity. Large sections of the pilings had little or no
barnacle growth and where barnacles were located, they were easily removed. There was some
spot corrosion where the coating had been gouged as a result of severe abrasion. However,
the rust did not extend beyond the damaged areas.
The epoxy pilings coated at approximately the same time with the same surface preparation
and exposed to the same service conditions did not fair nearly as well. The epoxy
blistered and delaminated in many spots. There were also large areas where the steel had
rusted through the coating. The barnacle growth was extensive and difficult to remove.
In 1991, the Port of New Orleans chose a 100% solids
polyurethane coating for corrosion protection of the steel pipe pilings for their
Nashville Wharf B project. The evaluation after 5 years of service life proved the
polyurethane coating is performing superbly.
Minor damage can be found on the pilings from the severe abrasion damage caused by
installation and in-service conditions. Even where the coating has been damaged, there is
only minimal undercutting. The expansion work continues at The Port of New Orleans. At
present, Wharf C is under construction which involves the addition of 1,000,000 square
feet to the Nashville Wharf structure.
However, for the Wharf C pilings, the choice was made to go with a lower cost fusion
bonded epoxy product. Upon visual inspection, the f.b.e.-coated pilings are not faring as
well as those protected with the polyurethane coating.
With the Wharf C construction nearing completion, the f.b.e.-coated pilings have been in
service for less than one year and show signs of more than "normal" wear and
tear. The inherent brittleness of the fusion bonded epoxy material allows for severe
damage to occur to the coating from the impact of the installation hammer.
Copyright © 1997 by Dr. Shiwei Guan
E-mail:
sguan@canada.com
This website is designed by myself and hosted by Get your own Free
Home Page.